Building for Our Future: Capital Improvement Project Status
The Capital Improvement Program includes dollars for renovations, modular classrooms, additions to existing schools, and construction of new schools.
Approximately two out of every three Capital Improvement Program dollars are earmarked for renovations, modular classrooms, additions of existing school facilities, and construction of new schools. This significant expenditure reflects the age of FCPS facilities and the School Board's commitment to ensuring that all schools contain the facilities necessary to support current educational programs. The schools listed below are some of the currently funded projects which are underway.
Bonnie Brae Elementary
Scope: Renovation with additions totaling approximately 126,600 SF. Additions include classrooms, art, interior courtyards, and site improvements.
Funding: 2019 Bond (Planning), 2021 Bond (Construction)
Architect: Samaha Associates, P.C.
Contractor: TBD
Current Status: In Permitting
Estimated Completion: Fall 2024
Braddock Elementary
Scope: Renovation with additions, totaling approximately 108,000 SF. Additions include classrooms, administrative offices, library, and site improvements.
Funding: 2017 Bond (Planning), 2019 Bond (Construction)
Architect: Bowie Gridley Architects
Contractor: Dustin Construction
Current Status: Under Construction
Estimated Completion: Fall 2023
Clifton Elementary School Feasibility School
-
Clifton Elementary School Feasibility Study 2021
View the Feasibility Study and Recommended Reuse of the Existing Facility.
Crossfield Elementary
Scope: Renovation including additions, totaling approximately 101,000 SF. Additions include a library and a main office.
Funding: 2019 Bond (Planning), 2021 Bond (Construction)
Architect: Moseley Architects
Contractor: TBD
Current Status: In Permitting
Estimated Completion: Winter 2024/2025
Fox Mill Elementary
Scope: Renovation including additions, totaling approximately 91,000 SF. Additions include classrooms, administrative offices, library, and site improvements.
Funding: 2017 Bond (Planning), 2019 Bond (Construction)
Architect: MTFA Architecture
Contractor: Howard Shockey
Current Status: Under Construction
Estimated Completion: Winter 2022/2023
Hybla Valley Elementary
Scope: Renovation including additions, totaling approximately 93,000 SF. Additions include classrooms, administrative offices, library, and site improvements.
Funding: 2017 Bond (Planning), 2019 Bond (Construction)
Architect: Maginniss + Del Ninno Architects
Contractor: Hess Construction
Current Status: In Construction
Estimated Completion: Spring 2023 Completion
Louise Archer Elementary
Scope: Renovation including additions, totaling approximately 104,000 SF. Additions include classrooms, administrative offices, library, and site improvements.
Funding: 2019 Bond (Planning), 2021 Bond (Construction)
Architect: Architecture, Inc.
Contractor: TBD
Current Status: In Permitting
Estimated Completion: Winter 2024/2025
Mosaic Elementary
Scope: Renovation with additions totaling approximately 122,000 SF. Scope to include classrooms, gymnasium, administration and cafeteria/kitchen expansion, and site improvements.
Funding: 2019 Bond (Planning), 2021 Bond (Construction)
Architect: Perkins Eastman
Contractor: TBD
Current Status: In Design
Estimated Completion: Winter 2024
Oak Hill Elementary
Scope: Renovation including additions, totaling approximately 104,000 SF. Additions include classrooms, administrative offices, library, and site improvements.
Funding: 2017 Bond (Planning), 2019 Bond (Construction)
Architect: Ballou Justice Upton Architects
Contractor: Whiting-Turner Contracting Company
Current Status: Under Construction
Estimated Completion: Winter 2023
Wakefield Forest Elementary
Scope: Renovation including additions, totaling approximately 103,000 SF. Additions include a library, classrooms, music room, administrative offices, cafeteria expansion, and site improvements.
Funding: 2019 Bond (Planning), 2021 Bond (Construction)
Architect: Rebecca Bostick Architect, Inc.
Contractor: TBD
Current Status: In Permitting
Estimated Completion: Summer 2024
Washington Mill Elementary
Scope: Renovation including additions, totaling approximately 97,200 SF. Additions include classrooms, administrative offices, library, and site improvements.
Funding: 2017 Bond (Planning), 2019 Bond (Construction)
Architect: Rebecca Bostick Architect, Inc.
Contractor: Meridian Construction
Current Status: Under Construction
Estimated Completion: Fall 2022
Cooper Middle
Scope: Renovation with additions, totaling approximately 179,000 SF. Additions include classrooms, library, administrative offices, and site improvements including parking.
Funding: 2015 Bond (Planning), 2019 Bond (Construction)
Architect: Perkins Eastman
Contractor: Keller Brothers, Inc.
Current Status: Under Construction
Estimated Completion: Fall 2023
Frost Middle
Scope: Renovation including additions, totaling approximately 206,000 SF. Additions include classrooms, administrative offices, library, and site improvements.
Funding: 2017 Bond (Planning), 2019 Bond (Construction)
Architect: Stantec
Contractor: RJ Crowley
Current Status: Under Construction
Estimated Completion: Fall 2023
Kilmer Middle Modular
Scope: New (10) classroom modular building approximately 11,800 SF. (+194,855 SF. existing building)
Funding: 2019 Bond
Architect: Fairfax County Public Schools
Contractor: Cooper Building Services, LLC
Current Status: Complete
Falls Church High
Scope: Renovation including additions, totaling approximately 429,000 SF. Additions include science classrooms, administrative offices, library, music rooms, and site improvements.
Funding: 2017 Bond (Planning), 2021 Bond (Construction)
Architect: Perkins Eastman
Contractor: TBD
Current Status: In Permitting
Estimated Completion: Summer 2026
Herndon High
Scope: Renovation including additions, totaling approximately 415,700 SF. Additions include science classrooms, administrative offices, library, music rooms, and site improvements.
Funding: 2013 Bond (Planning), 2015 Bond (Construction)
Architect: Hughes Group Architects
Contractor: Grunley Construction
Current Status: Complete
Justice High
Scope: Addition totaling approximately 46,000 SF and including science classrooms. Site and parking improvements also included.
Funding: 2017 Bond (Planning), 2019 Bond (Construction)
Architect: Hughes Group Architects
Contractor: TBD
Current Status: In Permitting
Estimated Completion: TBD
May 6 Community Meeting on Justice High School Addition - Details
Madison High
Scope: Addition totaling approximately 64,000 SF and including science classrooms and library.
Funding: 2017 Bond (Planning), 2019 Bond (Construction)
Architect: Hord Coplan Macht
Contractor: Meridian
Current Status: Under Construction
Estimated Completion: Fall 2022
Oakton High
Scope: Renovation including additions, totaling approximately 409,700 SF. Additions include science classrooms, administrative offices, library, music rooms, and site improvements including parking.
Funding: 2013 Bond (Planning), 2017 Bond (Construction)
Architect: Perkins Eastman
Contractor: Henley Construction Company, Inc.
Current Status: Under Construction
Estimated Completion: Fall 2022
West Potomac High
Scope: Addition totaling approximately 76,000 SF and including science classrooms and cafeteria.
Funding: 2017 Bond (Planning), 2019 Bond (Construction)
Architect: Architecture, Inc.
Contractor: Dustin Construction
Current Status: Under Construction
Estimated Completion: Fall 2022